ok here are some more updates, yesterday was prep day moving 30 bags concrete, mixer, water and etc. i need to do the job site which made it so much easier then trying to accomplished it all in one day.
started sunday morning 8am mixing 2 bags at a time then pouring the concrete in placed and spread it out evenly to the end.
finished 10:30am
got a chance to uncrate chiller, here are some pic's.
Tradewind 1.5hp 18,000BTU